(Bloomberg) — Taiwan has stopped approving knowledge facilities which can be greater than 5 MW north of Taoyuan, as there’s an inadequate energy provide within the area.
Whereas the island as an entire doesn’t have an electrical energy scarcity, there’s a bottleneck within the north, which is reliant on different areas for provide and desires extra grid infrastructure and new sources of electrical energy to fulfill rising demand, the Ministry of Financial Affairs mentioned in a Fb post. There have been no approvals of huge knowledge facilities within the north since September final 12 months, native media reported, citing the chairman of Taiwan Energy Firm.
Taiwan final month controversially shut one in all two remaining nuclear reactors because it seeks to free itself of the expertise by 2025, and the northern area’s atomic energy stations have already closed.
The transfer – pushed by issues following the 2011 Fukushima meltdown in Japan – has made power safety a key difficulty on the island, which additionally homes energy-guzzling chipmakers comparable to Taiwan Semiconductor Manufacturing Firm, which provides Apple and Nvidia Company.
Different grids within the area have voiced comparable issues about supplying heavy electrical energy customers. Singapore imposed a ban on new knowledge facilities in 2019 due to scarcity issues however lifted it in 2022.
Taiwan ought to “prioritize constructing knowledge facilities with an influence consumption of greater than 5 megawatts within the central and southern area the place there’s adequate renewable power and huge sources of power,” Taipower mentioned. That may enable industries to “cut back carbon emissions and improve worldwide competitiveness whereas matching the load with the facility provide facet,” the utility mentioned.