Managed IT service supplier Redcentric has accomplished a multi-million-pound electrical infrastructure improve as a part of a wider information centre refurbishment mission at its facility situated at Heathrow Company Park in London.
The mission, which included a UPS alternative, was part-funded by way of the Industrial Vitality Transformation Fund (IETF), now closed for purposes, which helps the deployment of applied sciences that allow companies with excessive vitality use to transition to a low-carbon future.
As a part of Redcentric’s high-profile mission, main UPS producer CENTIEL has delivered tools to guard an present 7 megawatts of essential load by way of its multi-award-winning, extremely environment friendly, true modular uninterruptible energy provide (UPS), StratusPowerTM. The deployment of this modular UPS expertise allows Redcentric to scale to 10.5 megawatts with out the necessity for any additional infrastructure change.
The ability, which is well-liked with FTSE 100 firms, is now seeing UPS effectivity enhancements from under 90% to above 97% for the reason that improve. This represents the potential to scale back greater than 8,000 tonnes of CO₂ emissions over the following 15 years, supporting ESG compliance for each Redcentric and its household-name purchasers.
Paul Hone, Knowledge Centre Services Director, Redcentric, confirmed, “Our London West colocation information centre is a strategically situated facility that provides cost-effective ISO-certified racks, cages, non-public suites, and full information halls, in addition to vital on-site workplace area. The information centre is powered by 100% renewable vitality, sourced solely from photo voltaic, wind and hydro.
“In 2023, we launched into the beginning of a full improve throughout the ability, which included {the electrical} infrastructure and dwell alternative of legacy UPS earlier than they reached finish of life. This a part of the mission has now been accomplished with zero downtime or disruption. At Redcentric, we satisfaction ourselves on the excessive degree of uptime throughout all of our information centres. The continual reinvestment into new tools to realize efficiencies now means we will proceed to supply our valued purchasers a 100% uptime assure at our London West facility.
“As well as, for 2026, we’re additionally planning an additional deployment of 12 megawatts of energy safety from two refurbished information halls being configured to assist AI workloads of the long run.”
Aaron Oddy, Gross sales Supervisor, Centiel, added, “A essential element of the mission was the strategic elimination of twenty-two megawatts of inefficient, legacy UPS techniques. By changing outdated expertise with the newest innovation, we’ve got dramatically improved effectivity, delivering rapid and substantial price financial savings.
“StratusPower affords an distinctive 97.6% effectivity, dramatically growing energy utilisation and lowering the info centre’s general carbon footprint – a key driver for Redcentric.
“The legacy tools was changed by Centiel’s StratusPower UPS system, that includes 14 x 500 kW modular UPS techniques. This delivered a major discount in bodily dimension, whereas delivering larger resilience, as a direct results of StratusPower’s award-winning, distinctive structure.
“StratusPower supplies an unprecedented degree of resilience and availability, guaranteeing near-zero system downtime, making certain the info centre can supply its purchasers the very best commonplace of energy safety. Standardising with this design throughout the positioning allows UPS modules to be seamlessly redeployed between techniques, making certain most asset utilisation and operational agility.”
Durata, a pacesetter in modular information centre options and significant energy infrastructure, accomplished the set up to the very best requirements.
Hone continued, “Environmental issues had been a key driver for us. StratusPower is a very modular answer, making certain environment friendly operating and upkeep of techniques. Lowering the requirement for main midlife service element replacements additional provides to its inexperienced credentials.
“With no commissioning points, zero reliability challenges or issues with the product, we’re already speaking to the Centiel workforce about how they will probably assist us with energy safety at our different websites.”