Friday, 20 Mar 2026
Subscribe
logo
  • Global
  • AI
  • Cloud Computing
  • Edge Computing
  • Security
  • Investment
  • Sustainability
  • More
    • Colocation
    • Quantum Computing
    • Regulation & Policy
    • Infrastructure
    • Power & Cooling
    • Design
    • Innovations
    • Blog
Font ResizerAa
Data Center NewsData Center News
Search
  • Global
  • AI
  • Cloud Computing
  • Edge Computing
  • Security
  • Investment
  • Sustainability
  • More
    • Colocation
    • Quantum Computing
    • Regulation & Policy
    • Infrastructure
    • Power & Cooling
    • Design
    • Innovations
    • Blog
Have an existing account? Sign In
Follow US
© 2022 Foxiz News Network. Ruby Design Company. All Rights Reserved.
Data Center News > Blog > Global Market > Edinburgh Council rejects ‘green’ data centre plan
Global Market

Edinburgh Council rejects ‘green’ data centre plan

Last updated: February 5, 2026 1:54 pm
Published February 5, 2026
Share
Edinburgh Council rejects ‘green’ data centre plan
SHARE

Plans for a big information centre on the previous Royal Financial institution of Scotland headquarters web site in Edinburgh have been thrown out by councillors. 

The proposals, introduced ahead by landowner Shelborn Asset Administration, lined the South Gyle web site at Redheughs Avenue and had been marketed as a ‘inexperienced’ information centre, alongside wider works together with a brand new public park. 

Whereas Shelborn was assured in its means to ship the info centre, the plans haven’t been with out scrutiny. Actually, simply days in the past, campaigners mounted a last-ditch effort to dam the challenge from transferring ahead. That marketing campaign centered on the ‘inexperienced’ features of the info centre, arguing that the usage of the positioning’s back-up mills might be equal to ‘100,000 idling cars-worth of diesel’ being burned

Officers backed it – however councillors weren’t satisfied

The unanimous refusal by the council’s improvement administration sub-committee will seemingly be a shock to Shelborn Asset Administration, after all of the council’s personal planning officers had really useful that the challenge go-ahead. 

Regardless of suggestions from their very own planning officers, councillors needed to wrestle with whether or not the scheme was suitable with its coverage route for the broader Edinburgh Park improvement – which was purported to shift away from a business-dominated atmosphere and in the direction of a extra mixed-use house that was higher built-in with the town. Finally, they determined that the info centre wasn’t conducive to these plans. 

Representatives for Shelborn Asset Administration tried to argue the broader advantages the info centre may have for a mixed-use improvement – noting that it will have the ability to use waste warmth from the info centre to provide houses and places of work which are constructed at Edinburgh Park. Nevertheless, councillors questioned how life like that profit was within the close to time period, and whether or not the scheme may meet the factors getting used to justify its ‘main scale’ standing.

See also  Colovore Launches Second 9MW Liquid-Cooled Data Center in Santa Clara

Was this truly a ‘inexperienced’ information centre?

Councillors additionally took difficulty with whether or not the info centre plans truly constituted as being ‘inexperienced’, as claimed by the builders. In line with Alys Mumford, a Inexperienced councillor that sits on the committee, “It’s solely inexperienced information centres which are thought of to be of main scale and due to this fact of nationwide significance and we’re instructed within the report that the very fact it’s nationwide infrastructure is the rationale why, on steadiness, it has been really useful despite the fact that it doesn’t adjust to a number of of our insurance policies.”

Councillor Mumford additionally argued it couldn’t be thought of a inexperienced information centre as a result of, she believed, it failed to satisfy a number of of the factors.

She stated, “On energy from renewable vitality sources, we’ve been instructed there’s something in place however we haven’t been given the figures on this, we haven’t been capable of hear from the facility suppliers.

“On making use of environment friendly applied sciences, we haven’t had that a lot reassurance across the air cooling system.

“Looking for to minimise water consumption – we all know there hasn’t been pre-engagement with Scottish Water and no actual element about cooling. If this was a severe plan, this could have been on the forefront of discussions.

“And re-use of warmth is the actually key one for extra. We had been instructed by the candidates this was one of many essential benefits for the council. We’re nowhere close to having the ability to realise this at present, so now we have to low cost that in the mean time.

See also  The Four Ps Reshaping Data Centers

“So if this isn’t a inexperienced information centre, which I consider it isn’t, there are main points with this proposal which might’t be balanced out by that nationwide consideration.”

She stated amongst different points, the plan would take away 1 / 4 of the timber on the positioning and the dimensions was ‘unacceptably massive and dominant on the skyline’.

Different councillors appeared to agree with Alys, in the end deciding that the info centre would fail to win its software for planning permission on the grounds that it didn’t meet the factors to be thought of ‘inexperienced’. 

What occurs subsequent for Shelborn is prone to come down as to whether it returns with a redesigned proposal that extra clearly meets the council’s coverage checks, or whether or not it pursues no matter attraction route is offered. In contrast to information centres in England, nevertheless, they might face a more durable time convincing the Authorities in Holyrood to overturn the native council’s resolution. 

Source link

Contents
Officers backed it – however councillors weren’t satisfiedWas this truly a ‘inexperienced’ information centre?
TAGGED: centre, Council, data, Edinburgh, green, Plan, rejects
Share This Article
Twitter Email Copy Link Print
Previous Article Lantronix and Safe Pro bring on-device AI threat detection to defense drones Lantronix and Safe Pro bring on-device AI threat detection to defense drones
Next Article Microsoft unveils method to detect sleeper agent backdoors Microsoft unveils method to detect sleeper agent backdoors
Leave a comment

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Your Trusted Source for Accurate and Timely Updates!

Our commitment to accuracy, impartiality, and delivering breaking news as it happens has earned us the trust of a vast audience. Stay ahead with real-time updates on the latest events, trends.
FacebookLike
TwitterFollow
InstagramFollow
YoutubeSubscribe
LinkedInFollow
MediumFollow
- Advertisement -
Ad image

Popular Posts

DeepSeek-V3, ultra-large open-source AI, outperforms Llama and Qwen on launch

Be part of our each day and weekly newsletters for the most recent updates and…

December 26, 2024

Codicent Raises First Funding

Codicent, a Gothenburg, and Molndal, Sweden-based AI startup building AI-driven logbooks to help companies manage…

February 8, 2024

SchoolAI Raises $25M in Series A Funding

SchoolAI, a Lehi, UT-based supplier of an AI platform for instructing and studying, raised $25M…

April 3, 2025

Cato Networks Empowers Service Providers with Private PoP for SASE Delivery

Cato Networks has unveiled Cato Personal PoP, a revolutionary resolution that enhances efficiency, management, and…

June 12, 2025

Only 9% of developers think AI code can be used without human oversight, BairesDev survey reveals

Senior software program builders are getting ready for a significant shift in how they work…

November 11, 2025

You Might Also Like

Cloud Computing Disaster Recovery Solutions Concept - Cloud DR - Services Companies Use for the Purpose of Backing Up Resources into a Cloud Environment - 3D Illustration
Global Market

Nile adds microsegmentation and native NAC to its secure NaaS platform

By saad
Planning delays continue to delay Tritax's Slough data centre
Global Market

Planning delays continue to delay Tritax’s Slough data centre

By saad
A photograph of a row of Ethernet cables plugged into ports, with a warning sign illuminated above one of the ports.
Global Market

Telnet vulnerability opens door to remote code execution as root

By saad
Could Telehouse be about to add a sixth data centre to its Docklands campus?
Global Market

Could Telehouse be about to add a sixth data centre to its Docklands campus?

By saad
Data Center News
Facebook Twitter Youtube Instagram Linkedin

About US

Data Center News: Stay informed on the pulse of data centers. Latest updates, tech trends, and industry insights—all in one place. Elevate your data infrastructure knowledge.

Top Categories
  • Global Market
  • Infrastructure
  • Innovations
  • Investments
Usefull Links
  • Home
  • Contact
  • Privacy Policy
  • Terms & Conditions

© 2024 – datacenternews.tech – All rights reserved

Welcome Back!

Sign in to your account

Lost your password?
We use cookies to ensure that we give you the best experience on our website. If you continue to use this site we will assume that you are happy with it.
You can revoke your consent any time using the Revoke consent button.